Facility cooling headers
Route the specified facility-water service to its equipment connection points.
Critical facilities / cooling interfaces
Coordinate facility-water headers and CDU connections with cooling duty, coolant requirements and commissioning access.
Application guide · design inputs
Application analysis
Separate the facility water system from the technology cooling system in the connection schedule. Record the fluid, water-quality limits, wetted materials, operating conditions and owner of each interface. Use the selected CDU and IT equipment connection specifications to define the equipment side.
Mark isolation, filling, sampling, service clearances and leak-monitoring interfaces on the layout. Define flushing, cleanliness and commissioning requirements before connection. Record redundancy, control behaviour and failure isolation in the facility cooling design.
Route the specified facility-water service to its equipment connection points.
Define connection boundaries, service access and commissioning responsibilities.
Plan staged connections with defined isolation and commissioning boundaries.
Concept arrangement / 04
Select a review point to inspect the source, controls and distribution of a representative utility module.
Facility side — Identify the facility-water conditions and owner of the interface.
Engineering review
| Design input | What it changes | Evidence to request |
|---|---|---|
| Cooling boundary | Keep FWS and TCS requirements distinct. | CDU drawings and equipment-specific material/water-quality limits. |
| Thermal duty | Size against the equipment’s load and flow requirements. | Heat-load schedule, temperatures and permitted pressure differential. |
| Leak strategy | Coordinate monitoring, isolation and physical separation from equipment. | Facilities risk review and leak-detection/control interfaces. |
| Commissioning | Agree cleanliness, filling and verification before connection. | Equipment supplier’s flushing, sampling and acceptance procedure. |
Part-number starting points
Review catalogue dimensions, materials and connection types alongside the service schedule. Add selected part numbers to your enquiry.
Specify the size, pipe outside diameter, material, seal, joining system and tool. Include the intended duty and required product acceptance documents with the enquiry.
Prepare the next conversation
Questions worth resolving
Document the CDU boundary and the independent fluid, material, pressure, temperature and cleanliness requirements on each side.
Review all wetted pipework, fittings, seals and connected equipment against the coolant composition and treatment specification.
Include redundancy, isolation, leak response, controls and commissioning criteria in the facility cooling design.